Centre des congrès in St-Hyacinthe

ABF has obtained the mandate for this new project, which consists in the construction of a building that will include up to 36 meeting rooms, the main one being large enough to accomodate close to 2,500 people.

Centre des congrès à St-Hyacinthe

Reinforcing steel required : +/- 450 tons

Beginning : End of October 2016

End : August 2017

Institut d'Acier d'Armature du QuébecReinforcing Steel Institute of CanadaimageThe Quebec Road Builders and Heavy Construction AssociationSaskatoon Construction AssociationOttawa Construction AssociationSudbury Construction AssociationToronto Consutruction Associationbronze-frISO 9001 - Licence RBQ : 1466-84D4-98